BMW 7_ая the E38 series from 1994 to 2002
1. Introduction
2. Governing bodies and operation receptions
3. Settings and routine maintenance of the car
4. Engine
5. Systems of cooling of the engine, heating, ventilation and air conditioning
6. A power supply system and production of the fulfilled gases
7. Systems of electric equipment of the engine
8. Manual box of gear shifting and coupling
9. Automatic transmission
9.1. General information
9.2. Search of malfunctions
9.3. Removal and AT installation and hydrotransformer
9.4. Removal and installation of the pallet of a case
9.5. Removal and PNP sensor installation
9.6. Removal and installation of the ATF filter and hydraulic block
9.7. Removal and installation Ý/m valves, regulators and sensors
9.8. Replacement of an arm of the mechanism of switching of AT modes
9.9. Adjustment of the balance weight of switching
9.10. Adjustment of the lever of the selector
9.11. Adjustment and check of blocking of the lever of the selector
10. Kardanny and power shafts, reducer, differential and stupichny assemblies
11. Brake system
12. Suspension bracket and steering
13. Body
14. Onboard electric equipment
15. Electric equipment schemes


9-3-snyatie-i-ustanovka-at-i-gidrotransformatora.html

9.3. Removal and AT installation and hydrotransformer

Removal

Below the description on an example of AT A5S 310Z of the M60/1 engine is provided.


 PERFORMANCE ORDER

  1. Disconnect a negative wire from the storage battery.
  2. Remove system of release of OG assembled, and also its thermofilters (see. Head of the Power supply system and production of the fulfilled gases).
  3. Remove arms of fastening of mudguards from both parties.
  1. On models to 08.1995 g вып. establish the selector lever in the situation "P" and establish the adaptation No. 24 5 240 on the control unit balance weight. Give a nut (1).

At installation adjust the selector lever.


  1. On models from 08.1995 g вып. give a nut (2, holding a clip (1).

At installation adjust the selector lever.


  1. Take out a screw-driver a clamp (1) and pull out draft (2).
  1. Remove the thermofilter on the left side of a beam of the forward bridge. Disconnect arms of fastening of oil pipelines from an engine case.
  1. Substitute capacity for collecting following oil, give fixture (1) and liberate tips of oil pipelines from AT case.

At assembly use new sealing rings of oil pipelines.

  1. Prop up AT by means of the No. No. 00 2 030/24 5 300 special adaptations.
  1. Disconnect electroconducting a lambda probes from a cross-section beam of fastening of AT (see. Head of the Power supply system and production of the fulfilled gases), turn out bolts of fastening and remove a cross-section beam of fastening of AT.
  1. Disconnect the driveshaft from AT and hang out it (see. Head Kardanny and power shafts, reducer, differential and stupichny assemblies).

  1. Separate sockets of electroconducting and take it from fastening brackets to AT case.
  1. Take out a cap.
  1. Special key No. 24 1 110 verify 4 bolts of fastening of the hydrotransformer.
  1. Turn out a bolt and take away down a cover of a wire of a positive conclusion of the storage battery.
  1. Insert the adaptation (whetstone) No. 23 3 030 between the pallet of a case of the engine and a beam of the forward bridge.
  2. To turn to the left forward wheels and lower AT.
  1. To prevent a vyskalzyvaniye of the hydrotransformer fix it concerning AT. For this purpose insert the adaptation No. 24 4 080 into a window (1) case of AT and hold them the hydrotransformer.
  1. Turn out bolts of fastening of AT, take away it back, pull out and lower AT.
  1. If necessary remove the hydrotransformer. For this purpose screw in it adaptations No. 24 4 000 and take out the hydrotransformer from AT.

Thus ATF follows.

Installation

 PERFORMANCE ORDER

  1. Installation is made upside-down. Pay attention to the next moments.
  2. At installation of the hydrotransformer do not allow damage of a sealing ring and the bearing. To insert the hydrotransformer into a case, slightly press on it and turn until dredging of the hydrotransformer will be not included into gearing with a power shaft of the oil pump. Press the hydrotransformer against the stop.
  3. To roll bolts of fastening of AT follows only together with washers.
  1. At AT installation the adaptation No. 24 2 300 should settle down coaxially to openings in the compensating coupling, and through a window of the pallet of a case there should be an access to an opening (1) compensating coupling. Screw the adaptation No. 24 2 300 in a carving opening and if necessary turn the hydrotransformer so that this opening appeared below.
  1. Be convinced available centering plugs. If necessary, take out centering plugs from a case of AT and insert into the block of cylinders. The damaged centering plugs replace.
  2. Upon termination of works check level of ATF and if necessary modify it (see. Head of Control and routine maintenance of the car).


«previous page
9.2. Search of malfunctions
following page»
9.4. Removal and installation of the pallet of a case