BMW 7_ая the E38 series from 1994 to 2002
1. Introduction
2. Governing bodies and operation receptions
3. Settings and routine maintenance of the car
4. Engine
4.1. General information and preparatory operations
4.2. Check of kompressionny pressure
4.3. Engine check by means of the vacuum gage
4.4. Petrol M60/1 and M60/2 engines
4.4.1. Removal and installation of a cover of a head of cylinders
4.4.2. Removal and installation of a head of cylinders, adjustment of phases GRM
4.4.3. Removal and installation of the top section of the pallet of a case
4.4.4. Removal and installation of the pallet of a case
4.4.5. Removal and installation of covers of a chain of GRM
4.4.6. Replacement of epiploons of a cranked shaft
4.4.7. Removal and flywheel installation
4.4.8. Removal and installation of belts of a drive of auxiliary units
4.4.9. Removal and installation of a damper of krutilny fluctuations and its nave
4.4.10. Removal and installation of the oil pump
4.4.11. Removal and installation of the inlet pipeline
4.4.12. Removal and installation of final collectors
4.4.13. Removal and engine installation
4.5. M62 engine
4.6. Diesel M57 engine
4.7. Diesel M67 engine
5. Systems of cooling of the engine, heating, ventilation and air conditioning
6. A power supply system and production of the fulfilled gases
7. Systems of electric equipment of the engine
8. Manual box of gear shifting and coupling
9. Automatic transmission
10. Kardanny and power shafts, reducer, differential and stupichny assemblies
11. Brake system
12. Suspension bracket and steering
13. Body
14. Onboard electric equipment
15. Electric equipment schemes




0c1943ba

4-4-13-snyatie-i-ustanovka-dvigatelya.html

4.4.13. Removal and engine installation

 PERFORMANCE ORDER

  1. Execute the actions described in paragraphs from 1 on 4 Section Removal and installation of the top section of the pallet of a case.
  2. Remove the lower part of an air purifier.
  3. Disconnect the union of the vacuum line from the amplifier of brakes (see an illustration).
  1. Turn out bolts of fastening of the polnopotochny oil filter and hang out it on the engine, without disconnecting pipelines.
  1. Disconnect from the fuel distributive highway bringing and returnable fuel hoses.
  1. If necessary disconnect an air hose (2) from the one-pass valve of system of decrease in toxicity of OG.
  1. Disconnect from a butterfly valve management cables.
  1. Separate the socket (2) and disconnect a vacuum hose (3) from the EVAP system valve.
  1. Separate the socket of electroconducting of the engine and take an electroconducting plait aside.
  2. Unclench a bracket of fastening of the diagnostic socket and hang out the socket.
  3. Remove the left and right thermofilters.
  4. Turn out drain jams of cooling liquid on the left and right parties of the block of cylinders.
  5. Remove a radiator of system of cooling (see. Head of System of cooling of the engine, heating, ventilation and conditioning.
  6. Remove RKPP or AT (see. Section Removal and installation of the top section of the pallet of a case or Removal and installation of the pallet of a case).
  7. Disconnect from a starter a positive wire of the storage battery and remove a starter (see. Head of System of electric equipment of the engine).
  8. Disconnect positive wires of the storage battery from a case, pillows of the left arm and from the generator.
  9. Remove a branch pipe обдува the generator (see an illustration).
  10. Remove a belt of a drive of the generator (see. The section Removal and installation of belts of a drive of auxiliary units), the pump GUR and a belt of a drive of the To/in compressor (see. Section Removal and installation of belts of a drive of auxiliary units).
  11. Disconnect the To/in compressor from a basic arm and suspend the compressor aside, without disconnecting from it a tube.
  1. Disconnect a weight wire from the right support of the engine and turn out the top nuts of the left and right pillows of support of the engine.
  1. Disconnect hoses from a collector of system of cooling.
  1. Remove final collectors (see. Section Removal and installation of final collectors).
  2. By means of the special elevating device take the engine from an impellent compartment, having lifted it for forward and back elevating eyes (see illustrations).

Do not damage components in an impellent compartment during engine lifting.

  1. Installation is made in sequence, return to an order of dismantle of components. Be convinced of integrity of pillows of support and if necessary replace them.
  2. After installation before start of the engine check levels of working liquids and if necessary modify them.
  3. Start the engine and make sure of absence of leakages of fuel and working liquids, and also in absence of abnormal noise and vibrations.
  4. Let's to the engine work on single turns, then muffle it and again check levels of working liquids.


«previous page
4.4.12. Removal and installation of final collectors
following page»
4.5. M62 engine